Estimation

Why Estimates Fail

Cause Mitigation
Optimism bias Use historical data, not gut
Missing scope List "obvious" tasks explicitly
Integration blindness Add 20-30% for glue code
Unknown unknowns Add buffer based on novelty
Interruptions Assume 60% focused time

Estimation Techniques

Three-Point Estimation

Expected = (Optimistic + 4xMostLikely + Pessimistic) / 6

Relative Sizing

Compare to known references:

  • "This is about twice as complex as Feature X"
  • Use Fibonacci (1, 2, 3, 5, 8, 13) to reflect uncertainty

Task Decomposition

  1. Break into tasks <=4 hours
  2. If can't decompose, spike first
  3. Sum tasks + 20% integration buffer

Effort Multipliers

Factor Multiplier
New technology 1.5-2x
Unclear requirements 1.3-1.5x
External dependencies (waiting on others) 1.2-1.5x
Legacy/undocumented code 1.3-2x
Production deployment 1.2x
First time doing X 2-3x
Context switching (other priorities) 1.3x
Yak shaving risk (unknown unknowns) 1.5x

Hidden Work Checklist

Always include time for:

  • Code review (20% of dev time)
  • Testing (30-50% of dev time)
  • Documentation (10% of dev time)
  • Deployment/config (varies)
  • Bug fixes from testing (20% buffer)
  • Interruptions / competing priorities

When to Re-Estimate

Re-estimate when:

  • Scope changes materially
  • Major unknown becomes known
  • Actual progress diverges >30% from estimate

Communicating Estimates

Good: "1-2 weeks, confidence 70%-main risk is the third-party API integration"

Bad: "About 2 weeks"

Always include:

  1. Range, not point estimate
  2. Confidence level
  3. Key assumptions/risks