# Estimation
|
|
|
|
## Why Estimates Fail
|
|
|
|
| Cause | Mitigation |
|
|
|-------|------------|
|
|
| Optimism bias | Use historical data, not gut |
|
|
| Missing scope | List "obvious" tasks explicitly |
|
|
| Integration blindness | Add 20-30% for glue code |
|
|
| Unknown unknowns | Add buffer based on novelty |
|
|
| Interruptions | Assume 60% focused time |
|
|
|
|
## Estimation Techniques
|
|
|
|
### Three-Point Estimation
|
|
```
|
|
Expected = (Optimistic + 4xMostLikely + Pessimistic) / 6
|
|
```
|
|
|
|
### Relative Sizing
|
|
Compare to known references:
|
|
- "This is about twice as complex as Feature X"
|
|
- Use Fibonacci (1, 2, 3, 5, 8, 13) to reflect uncertainty
|
|
|
|
### Task Decomposition
|
|
1. Break into tasks <=4 hours
|
|
2. If can't decompose, spike first
|
|
3. Sum tasks + 20% integration buffer
|
|
|
|
## Effort Multipliers
|
|
|
|
| Factor | Multiplier |
|
|
|--------|------------|
|
|
| New technology | 1.5-2x |
|
|
| Unclear requirements | 1.3-1.5x |
|
|
| External dependencies (waiting on others) | 1.2-1.5x |
|
|
| Legacy/undocumented code | 1.3-2x |
|
|
| Production deployment | 1.2x |
|
|
| First time doing X | 2-3x |
|
|
| Context switching (other priorities) | 1.3x |
|
|
| Yak shaving risk (unknown unknowns) | 1.5x |
|
|
|
|
## Hidden Work Checklist
|
|
|
|
Always include time for:
|
|
- [ ] Code review (20% of dev time)
|
|
- [ ] Testing (30-50% of dev time)
|
|
- [ ] Documentation (10% of dev time)
|
|
- [ ] Deployment/config (varies)
|
|
- [ ] Bug fixes from testing (20% buffer)
|
|
- [ ] Interruptions / competing priorities
|
|
|
|
## When to Re-Estimate
|
|
|
|
Re-estimate when:
|
|
- Scope changes materially
|
|
- Major unknown becomes known
|
|
- Actual progress diverges >30% from estimate
|
|
|
|
## Communicating Estimates
|
|
|
|
**Good:** "1-2 weeks, confidence 70%-main risk is the third-party API integration"
|
|
|
|
**Bad:** "About 2 weeks"
|
|
|
|
Always include:
|
|
1. Range, not point estimate
|
|
2. Confidence level
|
|
3. Key assumptions/risks
|